Wharf Improvement Project

Tudor Wharf Boat Ramp and Sea Wall – Town of Nahant
MGL c.30, § 39M – Public Works Construction Contracts over $25,000

Project Plans – Posted March 2016

EventDateTime
Conservation Commission HearingSept. 28, 20167:30 PM
Submit Ad to Central RegisterSept. 29, 2016By 4:00 PM
Ad Appears in Lynn Item
Ad Appears in Central Register
IFB Posted on Town Website
Oct. 5, 2016By 10:00 AM
Questions Received ByOct. 14, 20163:00 PM
Questions Answered ByOct. 19, 201610:00 AM
Bids Due ByOct. 26, 201610:00 AM
Notify Winner, Issue Notice of AwardNov. 4, 2016By 3:00 PM
Town BOS Signs Contract
Depends on when contractor returns
bonds/insurance/signed contract
Nov. 3, 2016 or
Nov. 17, 2016
7:30 PM
Issue Notice to ProceedNov. 19, 201610:00 AM
Work to BeginDec. 19, 2016
Work to be completed (no later than)Mar. 17, 2017